Biggest investment
Investment approved - 4,630 mln. euro for completion of Nuclear Power plant Units 3 and 4, Mochovce Nuclear Power Plant, amount spent at 31.12.2014 – 2, 911 mln euro., amount to spend – 1,719 mln euro.
Hours worked in 2014 exceeded 14,4 milion overall (out of wich 7,3 „direct“ manhours for construction) with the peak number of overall employees at the construction site (direct and indirect) amounting to more than 5.200 most of which coming from the Mochovce region.
Total number of hours worked from the beginning of the Project is some 36,6 milion overall (out of wich 20,0 „direct“ manhours for construction (November 2008 until the end of December 2014).
On site there working at around 150 contractors, some of 800 experts of Slovenské elektrárne and Enel.